April 27, 2008

Guest Bath 1

The Guest Bath Project is moving along. There were a couple of things that were a little weird. First up was the tile. They drywalled and then added concrete tile backerboard. Weird as usually you do one or the other.
Builders usually spec these houses down to the last nail and screw. There was a lot of extra labor involved in doing it this way.

Showerpre
I used a 4'' grinder with a diamond blade to cut the tile and board into chunks to get it out of here. This is the most time effective strategy, but has the down side of being really dirty. They used spray foam on the exterior wall to insulate. After 35 years, you can see the cracks in the foam. One other interesting bit is that it is brittle and disintegrates to the touch.
Showerpre1

The Framing
Having gotten that mess out of the way removing the rest of the drywall, we are down to the skeleton. The wet wall is 2x6'', which we will insulate as well as the rest of the bathroom walls. The outside wall is 2x4'' laid flat and attached with cut nails. The window being off center is a result of some bad design. The outside of the house has a pleasing balanced look, but as you can see the balance is gone inside.
Shower3

Tile Mystery Surprise
Here is a closeup of the wetwall and tub. See that gap? The tub is 60'', and the rough opening is 61'' This explains the tile mystery. They had to put the concrete board on this wall to overcome that framing gap. To make the bullnose tile detail come out they had to put concrete board on the other two walls, and get deep bullnose tiles to finish the ends. There was enough room with the plumbing stubs to move this wall in an inch, but they didn't and this was the result. Surprise, Surprise, Surprise...
Shower4
The Fix
The plumber showed up and replaced the old shower valve and moved the supply lines for the new toilet and pedestal sink.
So I furred out the wall with 1x2 strips, and will cover the entire area with green board. The shower area will be tiled from the tub to the ceiling.
Shower5

I mentioned that I am not fond Surprises. But this is what makes remodeling interesting.


Comments

Verify your Comment

Previewing your Comment

This is only a preview. Your comment has not yet been posted.

Working...
Your comment could not be posted. Error type:
Your comment has been posted. Post another comment

The letters and numbers you entered did not match the image. Please try again.

As a final step before posting your comment, enter the letters and numbers you see in the image below. This prevents automated programs from posting comments.

Having trouble reading this image? View an alternate.

Working...

Post a comment

Taping

  • Painting
    This is a short tutorial on Taping Drywall for the folks who want to tackle remodeling projects that involve drywall.

Drywall Patch

  • Second Coat
    This is a guide to patch holes that appear in drywall yourself.

Smoothwall

  • Smoothwall32
    This is a tutorial on refinishing walls. Specifically it is about making walls smooth, which is a result of moving into a house that has 'textured' walls.

Things

  • note
  • search

July 2009

Sun Mon Tue Wed Thu Fri Sat
      1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 29 30 31